What does the Installed Capital Cost include?
What does the Installed Capital Cost include?
FEDS project costing algorithms account for any materials, taxes, and labor costs applicable to a given retrofit measure. Additionally, 15% contractor overhead, 10% design cost, and 6% site level supervisory, inspection and overhead factors are applied, along with any multipliers specified on the regional costs screen under the financial options. Note that many of the cost factors reflect real regional variation, including labor rates, materials cost multipliers, and sales tax rates—with differentiation driven by the specified zip code. Each of these parameters are also able to be modified by the user, if appropriate.